Current project · Ravenna, Seattle
Ravenna Basement Remodel
The required inspections are approved and the drywall is hung. Taping and mudding are scheduled to begin November 13 and are expected to take a few days.
Project updated November 12, 2026
See the transformation ↓Project snapshot
Drywall hung · Finishing scheduled
- Location
- Ravenna, Seattle
- Project type
- Basement remodel
- Current phase
- Drywall finishing
01 · Original basement
Keep the starting point visible.
These two photographs preserve the original basement before the new slab, room layout, trade rough-ins and insulation transformed the space.


02 · Approved inspection stage
Open assemblies, reviewed before they are covered.
Framing, plumbing, electrical and insulation inspections have been approved. The required fire-code conditions for this stage were also confirmed through the inspection sequence. Safe’n’Sound insulation now fills the documented wall cavities while the ceiling and interior framing remain open for the final pre-drywall review.
Field feedback from the inspector described the work as clean, proper and well managed.
Room guide
- Media room
- The open living area organized around the existing stair.
- Mudroom
- The transition space at the basement entry door.
- Bathroom
- The room with the small window between the closet openings and the visible toilet flange.
- Laundry room
- The enclosed interior room without windows or an exterior door.












03 · Drywall hung
The room layout is now enclosed and easier to read.
Drywall now covers the walls and ceilings throughout the documented basement rooms, carrying the project forward from open framing and insulation into defined living areas, circulation paths and service spaces. Openings remain for doors, lighting, ventilation, plumbing and electrical finishes.
Taping and mudding are scheduled to begin November 13 and are expected to be completed over the following few days.









04 · What comes next
Finish the drywall, then complete the rooms.
After taping, mudding and sanding prepare the new drywall surfaces, painting, tile work, flooring, trim work and final touches will follow in construction order.
- 01Taping and mudding
- 02Painting
- 03Tile work
- 04Flooring
- 05Trim work and final touches
Publication safeguards
The project story stays private where it should.
- Homeowner names and exact address omitted
- No people or private documents shown
- Location metadata removed from every web image
- Inspection statements limited to confirmed approvals
Current-project journal
Follow the work—not just the final reveal.
Start with a conversation
What could your basement become?
Share what is not working and what you want your home to feel like. Christian will help identify the next step.